Tower Crane Dismantling Method Statement File
A Tower Crane Dismantling Method Statement is a critical safety and technical document outlining the step-by-step procedure for removing a tower crane from a construction site. It ensures the process is controlled, risks are managed, and all personnel follow a standardized sequence. Core Components of a Dismantling Method Statement Tower Crane Dismantling Procedure | PDF - Scribd
Step 1: Preparation (Duration: 1 day)
Trolley the tower crane to the minimum radius and engage the slew lock. tower crane dismantling method statement
Part 6: Environmental & Weather Protocols
| Condition | Action | |-----------|--------| | Wind speed > 20 mph (9 m/s) | Stop all lifts above 50ft height. | | Wind speed > 25 mph (11 m/s) | Complete stop – secure partial load. | | Rain / fog (visibility < 50m) | Stop work. | | Lightning within 10 miles | Stop work, evacuate crane area. | | Night work | Only permitted with full lighting (500 lux minimum). | A Tower Crane Dismantling Method Statement is a
- Count all slings, shackles, and tools – nothing left aloft.
- Inspect ground area for dropped fasteners or hydraulic fluid.
- Complete dismantling report including:
Dismantling Methods